DOULOS BUILT · M&F #2

Executive Construction Brief

3-Week
Look-Ahead

The schedule is shifting from enclosure and site closeout into permanent power, kitchen systems startup, millwork, and the sequential video-wall build.

3 critical handoffs Power, kitchen startup, video wall
4 video-wall stages Slab → steel → CMU → thin stone
7 overdue activities Still marked In Progress
Aug 5 key convergence CMU begins; millwork install starts

Schedule by week

What happens next

The first week carries the highest coordination load. Permanent power, kitchen systems, paving, millwork, and the video-wall foundation all overlap.

Week 01

July 27–August 2

Video wall slabJuly 27–31 · Fuller Concrete
CPS electrical meterJuly 28 · Permanent power milestone
Kitchen startup clusterHood July 29 · HVAC July 29–31
Exterior & site closeoutPella track, butter block, asphalt
Week 02

August 3–9

Video wall steelAugust 3–5 · South Tex Steel
Video wall CMU beginsAugust 5 · Ericstad Masonry
Millwork installationFabrication complete; field start August 5
Week 03

August 10–16

Video wall CMU completesScheduled through August 12
Thin stone beginsAugust 12–17 · carries beyond window
Protect finish sequenceConfirm access, materials, and clean handoff

Critical path

Video wall handoff sequence

Concrete slabJuly 27–31
Structural steelAugust 3–5
CMU wallAugust 5–12
Thin stoneAugust 12–17

Each activity releases the next. A slip in slab or steel installation directly moves masonry and finish work.

Executive attention

Risks and actions

Most schedule risk is not new work—it is unresolved status, missing ownership, and unconfirmed handoffs.

Watch items

High
Seven activities remain In Progress after their planned finish.

Fire sprinkler, storefront glass, brackets/plywood, kitchen drywall, Corten soffit, west parking curb, and patio/turf butter block.

High
Permanent power is the near-term gate.

CPS meter completion must be confirmed before HVAC startup and broader commissioning.

Watch
Blank ownership weakens field handoffs.

Pella track, millwork, paving, countertops, interior metal, ductwork, and coordination items need a clear Ball in Court.

Watch
Current statuses may be stale.

Storefront countertops are blank; several items remain Pending at or beyond planned dates. Board data was last updated July 21.